Huntersville Delivery No 2 — Power plant · Oil · North Carolina Mun Power Agny #1McDowell Creek Solar LLC — Under construction · Solar · NC · 2 MW · 6.3 mi awayAREP DATA CENTER — Under construction · Large load · NC · 8.9 mi awayHornet Solar — Under construction · Solar · NC · 73 MW · 11.1 mi awayCLT 16 12MW DATA CENTER — Under construction · Large load · NC · 11.1 mi awayCLT16 - Data Center — Filed · Large load · NC · 11.2 mi awayDLR Moores Chapel Mobile Crane (Charlotte data centre) — Filed · Large load · NC · 12.9 mi away
  • Combustion
  • Wind & solar
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Huntersville Delivery No 2

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2007
Net generation, 2025
1 MWh
Grid
12 kV to Town of Huntersville - (NC) (DUK)
Location
Mecklenburg County, North Carolina
Operated by
North Carolina Mun Power Agny #1SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2007 to 2025
Fuel burned MMBtu by year, 2007 to 2025
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
19 years since 2007
Unused energy
19 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
SERC
Report year
2025
Grid voltage kv
12.50
Transmission owner
Town of Huntersville - (NC)
Balancing authority code
DUK
Balancing authority name
Duke Energy Carolinas
Fuel burned (MMBtu), 2025478
Capacity factor, 20250.000
Net generation (MWh), 20251
Balancing authority codeDUK
Data notes (1)
  • Heat rate (Btu/kWh), 2025 not shown: computed 478000.0 outside 5000-30000 Btu/kWh

Timeline

  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
McDowell Creek Solar LLC Under construction Solar 6.3 mi 2
AREP DATA CENTER Under construction Large load 8.9 mi
Hornet Solar Under construction Solar 11.1 mi 73
CLT 16 12MW DATA CENTER Under construction Large load 11.1 mi
CLT16 - Data Center Filed Large load 11.2 mi
DLR Moores Chapel Mobile Crane (Charlotte data centre) Filed Large load 12.9 mi

Sources EIA-860M · EPA ICIS-NPDES · FAA OE/AAA