Show on map
Huntley — Power plant · Solar · Cubico USA, LLCMay Renewables — Postponed · Solar + storage · SC · 200 MW · 11.9 km awayOrange County Biomass LLC — Postponed · Biomass · SC · 35 MW · 12.8 km awayUlmer Solar — Postponed · Solar · SC · 22 MW · 20.9 km away15428 SGR 2A Data Center — Filed · Large load · SC · 21.0 km awayRowesville Rd Plant — Postponed · Gas, combustion turbine · SC · 9.6 MW · 22.8 km awayShining Sun Solar — Permitted · Solar · SC · 74 MW · 23.7 km away
  • Wind & solar
  • Loads
  • In development
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Power plant · Solar

Key facts

Power plant · Solarran 24% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2020
Net generation, 2025
157,719 MWh
Grid
230 kV to Dominion Energy South Carolina, Inc (SCEG)
Location
Orangeburg County, South Carolina
Operated by
Cubico USA, LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2020 to 2026

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Solar source: “Solar Photovoltaic”
Age
6 years since 2020
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100000804965
Location id
L100000804315
Eia plant ids
63271
Grid
Nerc region
SERC
Report year
2025
Grid voltage kv
230
Transmission owner
Dominion Energy South Carolina, Inc
Balancing authority code
SCEG
Balancing authority name
Dominion Energy South Carolina
Fuel burned (MMBtu), 2025538,137
Capacity factor, 20250.240
Net generation (MWh), 2025157,719
Balancing authority codeSCEG

Solar arrays

Array area (acres)
426.4
AC capacity (MW)
75
DC capacity (MW)
98.9
Mounting
Single-axis tracking
Site type
Greenfield
Began operating
2020

Source USPVDB

Source

  • USPVDBOpen license · retrieved Oct 25, 2026Map services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb

Attribution

Timeline

  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · GEM · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • GEMOpen license, with credit · retrieved Oct 26, 2026Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
  • USPVDBOpen license · retrieved Oct 25, 2026Map services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
May Renewables Postponed Solar + storage 11.9 km 200
Orange County Biomass LLC Postponed Biomass 12.8 km 35
Ulmer Solar Postponed Solar 20.9 km 22
15428 SGR 2A Data Center Filed Large load 21.0 km
Rowesville Rd Plant Postponed Gas, combustion turbine 22.8 km 9.6
Shining Sun Solar Permitted Solar 23.7 km 74

Sources EIA-860M · FAA OE/AAA

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • FAA OE/AAAOpen license · retrieved Nov 9, 2026