International Paper Co. - New Bern Mill: location. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
International Paper Co. - New Bern Mill
Power plant · Biomass
Key facts
Power plant · Biomassran 61% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2014
- Net generation, 2025
- 204,455 MWh
- Grid
- 115 kV to Duke Energy Progress - (NC) (CPLE)
- Location
- Craven County, North Carolina
- Operated by
- GFC - New Bern Mill
Operations
- Net generation, 2025
- 204,455
MWh - Fuel burned, 2025
- 8,603,186
MMBtu - Capacity factor, 2025
- 61.3
% - Heat rate, 2025
- Not stated
| Year | Net generation (MWh) | Fuel burned (MMBtu) | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|---|
| 2026 (8 of 12 months) | 132,487 | 5,597,723 | — | — |
| 2025 | 204,455 | 8,603,186 | 61.3% | — |
| 2024 | 190,133 | 8,756,811 | 56.8% | — |
| 2023 | 196,940 | 8,204,411 | 59.0% | — |
| 2022 | 203,000 | 8,274,596 | 60.8% | — |
| 2021 | 214,682 | 8,607,237 | 64.3% | — |
| 2020 | 218,229 | 8,646,655 | 65.2% | — |
| 2019 | 197,702 | 8,254,282 | 59.2% | — |
| 2018 | 201,720 | 8,641,989 | 60.4% | — |
| 2017 | 213,184 | 8,802,572 | 63.9% | — |
| 2016 | 224,144 | 9,082,978 | 67.0% | — |
| 2015 | 219,780 | 8,977,033 | 65.8% | — |
| 2014 | 205,193 | 9,026,440 | 61.5% | — |
| 2013 | 221,904 | 9,540,040 | 66.5% | — |
| 2012 | 208,876 | 8,781,027 | 62.4% | — |
| 2011 | 205,223 | 8,658,211 | 61.5% | — |
| 2010 | 203,799 | 8,815,421 | 61.1% | — |
| 2009 | 181,793 | 7,731,388 | 54.5% | — |
| 2008 | 213,563 | 9,838,247 | 63.8% | — |
| 2007 | 211,849 | 8,848,480 | 63.5% | — |
| 2006 | 223,943 | 10,271,933 | 67.1% | — |
| 2005 | 223,334 | 10,105,381 | 66.9% | — |
| 2004 | 217,992 | 9,033,900 | 65.1% | — |
| 2003 | 235,151 | 8,358,974 | 70.5% | — |
| 2002 | 243,435 | 9,789,596 | 72.9% | — |
| 2001 | 227,547 | 10,068,288 | 68.2% | — |
How these are worked out
Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.
Sources
3 sourcesSources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)