- Clean firm
- Operating
- 10 · 100 · 1,000 MW
Map
- Clean firm
- Operating
Johnson 2: location. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Johnson 2
Power plant · Hydro
Key facts
Power plant · Hydroran 32% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1941
- Net generation, 2025
- 62,993 MWh
- Grid
- 115 kV to Nebraska Public Power District (SWPP)
- Location
- Gosper County, Nebraska
- Operated by
- Central Nebraska Pub P&I DistSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Operations
- Net generation, 2025
- 62,993
MWh - Fuel burned, 2025
- 214,933
MMBtu - Capacity factor, 2025
- 32.0
% - Heat rate, 2025
- Not stated
| Year | Net generation (MWh) | Fuel burned (MMBtu) | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|---|
| 2025 | 62,993 | 214,933 | 32.0% | — |
| 2024 | 69,302 | 236,460 | 35.1% | — |
| 2023 | 64,558 | 220,273 | 32.8% | — |
| 2022 | 48,081 | 164,052 | 24.4% | — |
| 2021 | 67,776 | 599,411 | 34.4% | — |
| 2020 | 117,338 | 1,028,702 | 59.4% | — |
| 2019 | 141,424 | 1,259,381 | 71.8% | — |
| 2018 | 104,527 | 951,614 | 53.0% | — |
| 2017 | 106,778 | 983,744 | 54.2% | — |
| 2016 | 154,138 | 1,423,002 | 78.0% | — |
| 2015 | 145,596 | 1,356,810 | 73.9% | — |
| 2014 | 81,809 | 778,004 | 41.5% | — |
| 2013 | 56,442 | 538,512 | 28.6% | — |
| 2012 | 75,710 | 720,457 | 38.3% | — |
| 2011 | 147,548 | 1,433,576 | 74.9% | — |
| 2010 | 127,682 | 1,245,665 | 64.8% | — |
| 2009 | 57,246 | 558,720 | 29.0% | — |
| 2008 | 35,765 | 352,429 | 18.1% | — |
| 2007 | 41,138 | 406,607 | 20.9% | — |
| 2006 | 22,625 | 224,417 | 11.5% | — |
| 2005 | 28,740 | 287,371 | 14.6% | — |
| 2004 | 23,482 | 235,337 | 11.9% | — |
| 2003 | 29,299 | 300,051 | 14.9% | — |
| 2002 | 38,187 | 388,476 | 19.4% | — |
| 2001 | 64,472 | 666,189 | 32.7% | — |
How these are worked out
Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.