Show on map
Laurel — Power plant · Gas, reciprocating engine · City of Laurel - (NE)
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Gas, reciprocating engine

Key facts

Power plant · Gas, reciprocating engine Standby
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1970
Net generation, 2025
0 MWh
Grid
2 kV to Cedar-Knox Public Power Dist (SWPP)
Location
Cedar County, Nebraska
Operated by
City of Laurel - (NE)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, reciprocating engine source: “Natural Gas Internal Combustion Engine”
Age
56 years since 1970
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Eia status
By code
SB
Mw
3.50
Units
3
Standby mw
3.50
Status rule
majority_mw_standby
In service mw
3.50
Out of service mw
0
Fuel burned (MMBtu), 20250
Net generation (MWh), 20250
Balancing authority codeSWPP
Data notes (1)
  • Capacity factor, 2025 not shown: net generation 0.0 MWh is not positive (the plant consumed at least as much as it produced over the year)

Retirement

Capacity retired
1.2 MW
Generators retired
3
Capacity still in service
3.5 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
6Natural Gas Internal Combustion Engine0.2 MWRetiredFebruary 2014
3Natural Gas Internal Combustion Engine0.6 MWRetiredMarch 2016
4Natural Gas Internal Combustion Engine0.4 MWRetiredApril 2016

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
2 kV
Transmission or distribution system owner
Cedar-Knox Public Power Dist
Balancing authority
Southwest Power Pool
NERC region
MRO
Transmission lines within 25 km (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit 4 scheduled to retire, 0.4 MW · EIA-860M
  • Stated Unit 3 scheduled to retire, 0.6 MW · EIA-860M
  • Stated Unit 6 scheduled to retire, 0.2 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution