Show on map
Lime Kiln - Mccain 230 kV — Transmission lineFrederick-Carroll County Renewable Waste — Postponed · Waste to energy · MD · 56 MW · 1.1 mi awayIAD94 — Filed · Large load · MD · 2.8 mi awayFANNIE MAE UTC DATA CENTER — Built · Large load · MD · 5.3 mi away
  • Loads
  • In development
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Lime Kiln - Mccain 230 kV

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
230 kV
States crossed
US-MD
Owner (as stated)
Potomac Edison

Details

Who’s behind it

Owner
Potomac Edison

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Mapped route length (miles)
4
Substations at the ends (as the source names them)
Lime Kiln to Mccain
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
Owner, as the source states itpotomac edison
HIFLD line ID100240
Voltage class220-287 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Frederick-Carroll County Renewable Waste Postponed Waste to energy 1.1 mi 56
IAD94 Filed Large load 2.8 mi
FANNIE MAE UTC DATA CENTER Built Large load 5.3 mi

Sources EIA-860M · FAA OE/AAA · EPA ICIS-Air

Sources

Attribution