Show on map
Malden — Power plant · Oil · City of Malden - (MO)
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Standby
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1957
Net generation, 2025
68 MWh
Grid
69 kV to Southwestern Power Administration (SWPP)
Location
Dunklin County, Missouri
Operated by
City of Malden - (MO)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
69 years since 1957
Heat rate
11,676 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Eia status
By code
SB
Mw
15.90
Units
7
Standby mw
15.90
Status rule
majority_mw_standby
In service mw
15.90
Out of service mw
0
Fuel burned (MMBtu), 2025794
Capacity factor, 20250.001
Heat rate (Btu/kWh), 202511,676.5
Net generation (MWh), 202568
Balancing authority codeSWPP

Retirement

Capacity retired
1.4 MW
Generators retired
1
Capacity still in service
15.9 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Petroleum Liquids1.4 MWRetiredFebruary 2013

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
69 kV
Transmission or distribution system owner
Southwestern Power Administration
Balancing authority
Southwest Power Pool
NERC region
MRO
Transmission lines within 25 km (2)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit 1 scheduled to retire, 1.4 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source