Mare Branch: location and 3 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Mare Branch
Power plant · Solar
Key facts
Power plant · Solar Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2026
- Grid
- 230 kV to Florida Power & Light Co (FPL)
- Location
- DeSoto County, Florida
- Operated by
- Florida Power & Light CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Solar source: “Solar Photovoltaic”
- Age
- 0 years since 2026
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 40,146 |
| Capacity factor, 2025 | 0.018 |
| Net generation (MWh), 2025 | 11,766 |
| Balancing authority code | FPL |
Timeline
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Hardwood Hammock Under construction | Solar | 2.5 km | 74.5 |
| Joshua Creek Under construction | Solar | 2.5 km | 74.5 |
| County Line Under construction | Solar | 21.7 km | 74.5 |