Mickleton Station — Power plant · Gas, combustion turbine · Calpine New Jersey Generation LLCDeptford Solar One — Postponed · Solar · NJ · 3 MW · 10.2 km awayEQUINIX — Large load · PA · 18.0 km awayCROSS CONNECT SOLUTIONS — Built · Large load · PA · 18.1 km away365 DATA CENTERS — Built · Large load · PA · 18.3 km awayH5 DATA CENTERS — Built · Large load · PA · 18.3 km awayCarneys Point Solar 1 LLC — Under construction · Solar · NJ · 3 MW · 20.2 km awayJP MORGAN CHASE - 4001 GOVERNOR PRINTZ BLVD — Built · Large load · DE · 23.9 km away
  • Combustion
  • Wind & solar
  • Loads
  • Under construction
  • Operating
  • Retired
  • Stage not stated
  • Size not stated
  • 10 · 100 · 1,000 MW

Mickleton Station

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbineran 0% of 2023 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1974
Net generation, 2023
2,082 MWh
Grid
69 kV to Atlantic City Electric Co (PJM)
Location
Gloucester County, New Jersey

Output

Net generation MWh by year, 2002 to 2024
Fuel burned MMBtu by year, 2002 to 2024
  • Gas

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
Age
52 years since 1974
All 3 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Parents
Name
Constellation Energy Corp
Share pct
100
Gem entity id
E100001000208
Unit ids
G100000402551
Location id
L100000401771
Eia plant ids
8008
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110015062206
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1001184
Balancing authority codePJM

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
June 2024
Capacity retired
71.2 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
MICKNatural Gas Fired Combustion Turbine71.2 MWRetiredJune 2024

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
69 kV
Transmission or distribution system owner
Atlantic City Electric Co
Balancing authority
PJM Interconnection, LLC
NERC region
RFC
Transmission lines within 25 km (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Calpine New Jersey Generation LLC Operator EIA-860M
Calpine Corporation Owner 100.0% Dec 31, 2023 EPA GHGRP

Timeline

  • Stated Unit MICK scheduled to retire, 71.2 MW · EIA-860M
  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • GEMOpen license, with credit · retrieved Oct 26, 2026Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
  • LBNLOpen license, with credit · retrieved Nov 9, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory
  • EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Deptford Solar One Postponed Solar 10.2 km 3
EQUINIX Unknown Large load 18.0 km
CROSS CONNECT SOLUTIONS Built Large load 18.1 km
365 DATA CENTERS Built Large load 18.3 km
H5 DATA CENTERS Built Large load 18.3 km
Carneys Point Solar 1 LLC Under construction Solar 20.2 km 3
JP MORGAN CHASE - 4001 GOVERNOR PRINTZ BLVD Built Large load 23.9 km

Sources EIA-860M · EPA ICIS-Air

Sources

Attribution