Milagro Cogeneration Plant
Power plant · Gas, combustion turbine
Key facts
Power plant · Gas, combustion turbineran 23% of 2015 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1981
- Net generation, 2015
- 246,370 MWh
- Grid
- 115 kV to City of Farmington - (NM) (WALC)
- Location
- San Juan County, New Mexico
- Operated by
- Harvest Midstream CO
Output
- Gas
Details
Who’s behind it
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
- Age
- 45 years since 1981
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| EPA greenhouse gas reporting (GHGRP) |
|
| Balancing authority code | WALC |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- March 2016
- Capacity retired
- 121.6 MW
- Generators retired
- 4
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| GENA | Natural Gas Fired Combustion Turbine | 30.4 MW | Retired | March 2016 |
| GENB | Natural Gas Fired Combustion Turbine | 30.4 MW | Retired | March 2016 |
| GO1A | Natural Gas Fired Combustion Turbine | 30.4 MW | Retired | March 2016 |
| GO1B | Natural Gas Fired Combustion Turbine | 30.4 MW | Retired | March 2016 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 115 kV
- Transmission or distribution system owner
- City of Farmington - (NM)
- Balancing authority
- Western Area Power Administration - Desert Southwest Region
- NERC region
- WECC
Transmission lines within 15 mi (3)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| HARVEST MIDSTREAM CO | Operator | EIA-860M | ||
| Harvest Pipeline Company | Owner | 100.0% | Dec 31, 2023 | EPA GHGRP |
Timeline
- Stated Units GENA, GENB, GO1A, GO1B scheduled to retire, 121.6 MW · EIA-860M
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)