Millwood 345 kV line: route and 5 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Millwood 345 kV line
Transmission line
- Mapped route length
- Mapped route length: sourceLBNL · Open license, with creditmiles
- Voltage
- 345 kV
- States crossed
- US-NY
- Owner (as stated)
- Consolidated Edison Of New York
Details
Who’s behind it
- Owner
- Consolidated Edison Of New York
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Mapped route length (miles)
- 9
- Substations at the ends (as the source names them)
- Millwood
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
| Attribute | Value |
|---|---|
| Owner, as the source states it | consolidated edison of new york |
| HIFLD line ID | 148050 |
| Voltage class | 345 kV |
Sources
1 sourceSources LBNL
Sources
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
Around this line
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| ORANGETOWN DATA CENTER Built | Large load | 7.7 mi | |
| DATA CENTER BUILDING EXPANSION Under construction | Large load | 8.0 mi | |
| Bowline Point Postponed | Gas, combined cycle | 8.8 mi | 750 |
| Eastern BlueBird Clean Energy LLC Under construction | Storage | 13.2 mi | 4.4 |
| Northern Cardinal Clean Energy, LLC Under construction | Storage | 13.2 mi | 4.4 |
Sources EPA ICIS-Air · EPA ICIS-NPDES · EIA-860M