- Combustion
- Retired
- 10 · 100 · 1,000 MW
Map
- Combustion
- Retired
Minden: location. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Minden
Power plant · Gas, steam turbine
Key facts
Power plant · Gas, steam turbine Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1955
- Net generation, 2017
- 0 MWh
- Location
- Webster County, Louisiana
- Operated by
- City of Minden - (LA)SourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
- Oil
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, steam turbine source: “Natural Gas Steam Turbine”
- Age
- 71 years since 1955
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Balancing authority code | MISO |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- August 2017
- First unit retired
- January 2015
- Capacity retired
- 35.4 MW
- Generators retired
- 7
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| 3 | Petroleum Liquids | 2.5 MW | Retired | January 2015 |
| 4 | Petroleum Liquids | 2.5 MW | Retired | January 2015 |
| 5 | Petroleum Liquids | 1.4 MW | Retired | January 2015 |
| 7 | Petroleum Liquids | 2 MW | Retired | January 2015 |
| 1 | Natural Gas Steam Turbine | 12.5 MW | Retired | August 2017 |
| 2 | Natural Gas Steam Turbine | 12.5 MW | Retired | August 2017 |
| 6 | Petroleum Liquids | 2 MW | Retired | August 2017 |
By technology
| Technology | Retired | Scheduled to retire |
|---|---|---|
| Natural Gas Steam Turbine | 25 MW | |
| Petroleum Liquids | 10.4 MW |
Grid
EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).- Balancing authority
- MISO
Transmission lines within 25 km (1)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Units 1, 2, 6 scheduled to retire, 27 MW · EIA-860M
- Stated Units 3, 4, 5, 7 scheduled to retire, 8.4 MW · EIA-860M
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory