Miramar — Power plant · Gas, combustion turbine · NRG Cabrillo Power Ops Inc
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbineran 1% of 2016 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1972
Net generation, 2016
2,624 MWh
Location
San Diego County, California
Operated by
NRG Cabrillo Power Ops IncSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Operations

Net generation, 2016
2,624MWh
Fuel burned, 2016
42,106MMBtu
Capacity factor, 2016
0.6%
Heat rate, 2016
16,046Btu/kWh
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
20162,62442,1060.6%16,046
20153,20247,4470.8%14,818
20145,30891,4201.2%17,223
20132,56043,7560.6%17,092
20123,71461,7820.9%16,635
20112,22841,4870.5%18,621
20102,29737,2610.5%16,222
20091,79031,9870.4%17,870
200888615,9800.2%18,036
20073,62661,2620.8%16,895
20062,18341,3850.5%18,958
20052,74850,8720.6%18,512
20045,643100,6091.3%17,829
20034,59362,0641.1%13,513
20023,96063,4870.9%16,032
200130,274526,8747.0%17,404
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

2 sources

Sources EIA-860M · EIA

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)

Every source and license · Attribution

View at source