Show on map
Missouri S&T - Power Plant — Power plant · Oil · Missouri University of Science and Technology
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Missouri S&T - Power Plant

Power plant · Oil

Key facts

Power plant · Oil Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1951
Net generation, 2018
0 MWh
Location
Phelps County, Missouri
Operated by
Missouri University of Science and TechnologySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2014 to 2018
Fuel burned MMBtu by year, 2014 to 2018
  • Coal
  • Oil
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
75 years since 1951
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeMISO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2018
First unit retired
May 2014
Capacity retired
1.5 MW
Generators retired
2
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
500KConventional Steam Coal0.5 MWRetiredMay 2014
1000Petroleum Liquids1 MWRetiredDecember 2018
By technology
Nameplate capacity retired or scheduled to retire, by technology
TechnologyRetiredScheduled to retire
Petroleum Liquids1 MW
Conventional Steam Coal0.5 MW

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
MISO
Transmission lines within 15 mi (5)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit 1000 scheduled to retire, 1 MW · EIA-860M
  • Stated Unit 500K scheduled to retire, 0.5 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source