Montgomery County Oaks LFGE Plant — Power plant · Biomass · CB&I
  • Bioenergy
  • Retired
  • 10 · 100 · 1,000 MW

Montgomery County Oaks LFGE Plant

Power plant · Biomass

Key facts

Power plant · Biomass Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2009
Net generation, 2022
0 MWh
Location
Montgomery County, Maryland
Operated by
CB&ISourceEIA-860M Preliminary Monthly Electric Generator Inventory

Operations

Net generation, 2022
0MWh
Fuel burned, 2022
0MMBtu
Capacity factor, 2022
Not stated
Heat rate, 2022
Not stated
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
202200——
2021 (7 of 12 months)6,34997,465—15,351
202011,375212,48454.0%18,680
201912,586214,29059.9%17,026
201813,453230,49464.0%17,133
201713,915203,48466.2%14,623
201612,601175,04959.8%13,892
201511,929147,28256.7%12,347
201416,392233,17678.0%14,225
201318,632258,96188.6%13,899
201217,787204,64684.4%11,505
201116,287179,42277.5%11,016
201015,233189,58572.5%12,446
20098,24873,48239.2%8,909
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

2 sources

Sources EIA-860M · EIA

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • EIAOpen license · retrieved Nov 27, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)

Every source and license · Attribution

View at source