Mountain Lake

Power plant · Wind

Key facts

Power plant · Windran 25% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2007
Net generation, 2025
2,599 MWh
Grid
69 kV to City of Mountain Lake - (MN) (MISO)
Location
Cottonwood County, Minnesota
Operated by
City of Mountain Lake - (MN)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2002 to 2025
Fuel burned MMBtu by year, 2002 to 2025
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Wind source: “Onshore Wind Turbine”
Age
19 years since 2007
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100001019638
Location id
L100001017649
Eia plant ids
1998
Fuel burned (MMBtu), 202512,380
Capacity factor, 20250.247
Net generation (MWh), 20252,599
Balancing authority codeMISO
Data notes (1)
  • Heat rate (Btu/kWh), 2025 not shown: computed 4763.4 outside 5000-30000 Btu/kWh

Wind turbines

Turbines
1
Turbine capacity (MW)
1.2
Turbine models
1 Suzlon S64-1.25
Hub height (m)
75
Rotor diameter (m)
64
Year online
2007

Source U.S. Wind Turbine Database

Source

  • U.S. Wind Turbine DatabaseOpen license · retrieved Oct 25, 2026Map services and data are available from U.S. Wind Turbine Database, provided by the U.S. Geological Survey, American Clean Power Association, and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uswtdb

Attribution

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
8 MW
Generators retired
5
Capacity still in service
1.2 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
4Petroleum Liquids2 MWRetiredJanuary 2023
2Natural Gas Internal Combustion Engine1.1 MWRetiredJanuary 2026
5Natural Gas Internal Combustion Engine1.3 MWRetiredSeptember 2026
6Petroleum Liquids1.8 MWRetiredSeptember 2026
7Petroleum Liquids1.8 MWRetiredSeptember 2026
By technology
Nameplate capacity retired or scheduled to retire, by technology
TechnologyRetiredScheduled to retire
Petroleum Liquids5.6 MW
Natural Gas Internal Combustion Engine2.4 MW
Retirement changes (1)
  • Retired seen 2026-10-24 4.9 MW unit 5 (Natural Gas Internal Combustion Engine, 1.3 MW): September 2026; unit 6 (Petroleum Liquids, 1.8 MW): September 2026; unit 7 (Petroleum Liquids, 1.8 MW): September 2026

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
69 kV
Transmission or distribution system owner
City of Mountain Lake - (MN)
Balancing authority
Midcontinent Independent Transmission System Operator, Inc..
NERC region
MRO
Transmission lines within 15 mi (4)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Retired · EIA-860M
  • Stated Units 5, 6, 7 scheduled to retire, 4.9 MW · EIA-860M
  • Stated Unit 2 scheduled to retire, 1.1 MW · EIA-860M
  • Stated Unit 4 scheduled to retire, 2 MW · EIA-860M
  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · LBNL · U.S. Wind Turbine Database · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • GEMOpen license, with credit · retrieved Oct 26, 2026Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • U.S. Wind Turbine DatabaseOpen license · retrieved Oct 25, 2026Map services and data are available from U.S. Wind Turbine Database, provided by the U.S. Geological Survey, American Clean Power Association, and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uswtdb
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source