Power plant · Hydro

Key facts

Power plant · Hydroran 5% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1953
Net generation, 2025
11,597 MWh
Grid
69 kV to Central Hudson Gas & Elec Corp (NYIS)
Location
Sullivan County, New York

Output

Net generation MWh by year, 2001 to 2025

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Hydro source: “Conventional Hydroelectric”
Age
73 years since 1953
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
NPCC
Report year
2025
Grid voltage kv
69
Transmission owner
Central Hudson Gas & Elec Corp
Balancing authority code
NYIS
Balancing authority name
New York Independent System Operator
Fuel burned (MMBtu), 202539,569
Capacity factor, 20250.053
Net generation (MWh), 202511,597
Balancing authority codeNYIS

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
NEW YORK POWER AUTHORITY Operator EIA-860M
City of New York Owner 100.0% Dec 31, 2025 EIA-860

Timeline

  • In service · EIA-860M

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Cypert - Fallsburg I Under construction Solar 3.1 mi 5

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution