Newberry — Power plant · Oil · Newberry Water & Light Board
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oil Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1948
Net generation, 2023
0 MWh
Location
Luce County, Michigan
Operated by
Newberry Water & Light BoardSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2023
Fuel burned MMBtu by year, 2001 to 2023
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
78 years since 1948
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeMISO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
March 2023
Capacity retired
5.5 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Petroleum Liquids3 MWRetiredMarch 2023
2Petroleum Liquids0.7 MWRetiredMarch 2023
4Petroleum Liquids1.8 MWRetiredMarch 2023

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
MISO
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2, 4 scheduled to retire, 5.5 MW · EIA-860M
  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source