Show on map
Nodaway — Power plant · Gas, combustion turbine · Associated Electric Coop, Inc
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbineran 1% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1999
Net generation, 2025
38,936 MWh
Grid
161 kV to Associated Electric Coop, Inc (AECI)
Location
Nodaway County, Missouri
Operated by
Associated Electric Coop, IncSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Operations

Net generation, 2025
38,936MWh
Fuel burned, 2025
473,886MMBtu
Capacity factor, 2025
1.4%
Heat rate, 2025
12,171Btu/kWh
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
202538,936473,8861.4%12,171
202427,430345,0541.0%12,579
202312,118155,4640.4%12,829
202220,004254,5260.7%12,724
202112,718146,4670.5%11,516
20208,70187,8360.3%10,095
20198,824109,4060.3%12,399
201810,988137,3400.4%12,499
20171,11912,9690.0%11,590
20161,74119,3010.1%11,086
20151,93326,7580.1%13,843
20143,48541,0320.1%11,774
20131,62622,5300.1%13,856
201219,252240,7720.7%12,506
20116,40882,5680.2%12,885
20106,19676,1640.2%12,292
20092,80536,9660.1%13,179
20081,59420,9350.1%13,134
20078,683104,1110.3%11,990
200628,744344,3311.0%11,979
20053,50541,9380.1%11,965
200492611,1080.0%11,996
20038,11686,8110.3%10,696
200221,412240,3570.8%11,225
200158,612687,4012.1%11,728
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

2 sources

Sources EIA-860M · EIA

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)

Every source and license · Attribution

View at source