North Riley

Power plant · Gas, reciprocating engine

Key facts

Power plant · Gas, reciprocating engineran 19% of 2005 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1990
Net generation, 2005
4,983 MWh
Location
Gaines County, Texas
Operated by
Pure ResourcesSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2002 to 2005
Fuel burned MMBtu by year, 2002 to 2005
  • Gas

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, reciprocating engine source: “Natural Gas Internal Combustion Engine”
Age
36 years since 1990

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
September 2005
Capacity retired
3 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN1Natural Gas Internal Combustion Engine1 MWRetiredSeptember 2005
GEN2Natural Gas Internal Combustion Engine1 MWRetiredSeptember 2005
GEN3Natural Gas Internal Combustion Engine1 MWRetiredSeptember 2005

Grid

Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.
Transmission lines within 15 mi (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units GEN1, GEN2, GEN3 scheduled to retire, 3 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · OpenStreetMap · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

© OpenStreetMap contributors

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • OpenStreetMapOpen license, with credit · retrieved Oct 10, 2026© OpenStreetMap contributors. Power lines, cables and substations filtered and reshaped by Inframation from the OpenStreetMap elements in Overture Maps' base/infrastructure theme; this derived database is available under the Open Database License 1.0 as GeoParquet files at https://tiles.inframation.io/grid/osm-power/ (latest.json names the current version's files; licence: https://www.openstreetmap.org/copyright)
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Gaines County Postponed Gas, combustion turbine 13.3 mi 225

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026