Show on map
Norton — Power plant · Gas, reciprocating engine · City of Norton
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Gas, reciprocating engine

Key facts

Power plant · Gas, reciprocating engine Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1955
Net generation, 2010
0 MWh
Location
NORTON County, Kansas
Operated by
City of NortonSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2010
Fuel burned MMBtu by year, 2001 to 2010
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, reciprocating engine source: “Natural Gas Internal Combustion Engine”
Age
71 years since 1955

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
August 2011
Capacity retired
11.2 MW
Generators retired
5
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Natural Gas Internal Combustion Engine1 MWRetiredAugust 2011
2Natural Gas Internal Combustion Engine1.5 MWRetiredAugust 2011
3Natural Gas Internal Combustion Engine2.7 MWRetiredAugust 2011
4Natural Gas Internal Combustion Engine3.5 MWRetiredAugust 2011
5Petroleum Liquids2.5 MWRetiredAugust 2011
By technology
Nameplate capacity retired or scheduled to retire, by technology
TechnologyRetiredScheduled to retire
Natural Gas Internal Combustion Engine8.7 MW
Petroleum Liquids2.5 MW

Grid

Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2, 3, 4, 5 scheduled to retire, 11.2 MW · EIA-860M
  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source