Show on map
- Wind & solar
- Under construction
- Operating
- 10 · 100 · 1,000 MW
Map
- Wind & solar
- Under construction
- Operating
Oberon IB: location and 4 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Oberon IB
Power plant · Solar
Key facts
Power plant · Solarran 24% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2020
- Net generation, 2025
- 61,946 MWh
- Grid
- 138 kV to Oncor Electric Delivery Company LLC (ERCO)
- Location
- Ector County, Texas
- Operated by
- Oberon Solar IB
Output
Details
Who’s behind it
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Solar source: “Solar Photovoltaic”
- Age
- 6 years since 2020
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 211,361 |
| Capacity factor, 2025 | 0.236 |
| Net generation (MWh), 2025 | 61,946 |
| Balancing authority code | ERCO |
Solar arrays
Solar arrays
The array area counts panels and inverters only, not buildings, fences or the whole site.
- Array area (acres)
- 175
- AC capacity (MW)
- 30
- DC capacity (MW)
- 37.3
- Mounting
- Single-axis tracking
- Site type
- Greenfield
- Began operating
- 2020
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Oberon Solar IB | Operator | EIA-860M | ||
| 174 Power Global Corp. | Owner | 100.0% | Dec 31, 2025 | EIA-860 |
Timeline
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M
- USPVDBMap services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Texas Clean Energy Project Postponed | Gas, other | 7.4 mi | 400 |
| Rockhound D Under construction | Solar | 10.6 mi | 28 |
| Rockhound A Under construction | Solar | 10.7 mi | 245 |
| Rockhound C Under construction | Solar | 10.7 mi | 61 |
Sources EIA-860M