Ocotillo Windpower — Power plant · Wind · Deriva EnergyCannibal Draw Solar and Storage — Contracted · Solar + storage · TX · 248.1 MW · 9.0 mi awayWallie Storage — Postponed · Storage · TX · 200 MW · 12.8 mi awayBhalu — Studied · Storage · TX · 205.5 MW · 13.5 mi awayHoney Mesquite Wind, LLC — Under construction · Wind · TX · 180.5 MW · 14.2 mi away
  • Wind & solar
  • Storage
  • In development
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Ocotillo Windpower

Power plant · Wind

Key facts

Power plant · Windran 15% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2008
Net generation, 2025
79,406 MWh
Grid
138 kV to Oncor Electric Delivery Company LLC (ERCO)
Location
Howard County, Texas
Operated by
Deriva Energy

Output

Net generation MWh by year, 2008 to 2025

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Wind source: “Onshore Wind Turbine”
Age
18 years since 2008
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100000909061, G100001023470
Location id
L100000906727
Eia plant ids
56959
Grid
Nerc region
TRE
Report year
2025
Grid voltage kv
138
Transmission owner
Oncor Electric Delivery Company LLC
Balancing authority code
ERCO
Balancing authority name
Electric Reliability Council of Texas, Inc.
Fuel burned (MMBtu), 2025270,934
Capacity factor, 20250.154
Net generation (MWh), 202579,406
Balancing authority codeERCO

Wind turbines

Turbines
26
Turbine capacity (MW)
54.6
Turbine models
26 Suzlon S88
Hub height (m)
79
Rotor diameter (m)
88
Year online
2008

Source U.S. Wind Turbine Database

Source

  • U.S. Wind Turbine DatabaseOpen license · retrieved Oct 25, 2026Map services and data are available from U.S. Wind Turbine Database, provided by the U.S. Geological Survey, American Clean Power Association, and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uswtdb

Attribution

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Deriva Energy Operator EIA-860M
Ocotillo Windpower LP Owner 100.0% Dec 31, 2025 EIA-860

Timeline

  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · U.S. Wind Turbine Database · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Cannibal Draw Solar and Storage Contracted Solar + storage 9.0 mi 248.1
Wallie Storage Postponed Storage 12.8 mi 200
Bhalu Studied Storage 13.5 mi 205.5
Honey Mesquite Wind, LLC Under construction Wind 14.2 mi 180.5

Sources ERCOT · EIA-860M

Sources

  • ERCOTOpen license · retrieved Nov 4, 2026
  • EIA-860MOpen license · retrieved Nov 4, 2026