Show on map
Ormesa IH — Power plant · Geothermal · Ormat Nevada IncImperial Sun Solar — Filed · Solar + storage · CA · 200 MW · 7.4 mi away
  • Clean firm
  • Wind & solar
  • In development
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Geothermal

Key facts

Power plant · Geothermalran 22% of 2017 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1989
Net generation, 2017
27,243 MWh
Grid
92 kV to Imperial Irrigation District (IID)
Location
Imperial County, California
Operated by
Ormat Nevada IncSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2017

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Geothermal source: “Geothermal”
Age
37 years since 1989
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeIID

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2017
Capacity retired
14.4 MW
Generators retired
12
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
OE11Geothermal1.2 MWRetiredDecember 2017
OE12Geothermal1.2 MWRetiredDecember 2017
OE13Geothermal1.2 MWRetiredDecember 2017
OE14Geothermal1.2 MWRetiredDecember 2017
OE15Geothermal1.2 MWRetiredDecember 2017
OE16Geothermal1.2 MWRetiredDecember 2017
OE21Geothermal1.2 MWRetiredDecember 2017
OE22Geothermal1.2 MWRetiredDecember 2017
OE23Geothermal1.2 MWRetiredDecember 2017
OE24Geothermal1.2 MWRetiredDecember 2017
OE25Geothermal1.2 MWRetiredDecember 2017
OE26Geothermal1.2 MWRetiredDecember 2017

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
92 kV
Transmission or distribution system owner
Imperial Irrigation District
Balancing authority
Imperial Irrigation District
NERC region
WECC
Transmission lines within 15 mi (2)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units OE11, OE12, OE13, OE14, OE15, OE16, OE21, OE22, OE23, OE24, OE25, OE26 scheduled to retire, 14.4 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Imperial Sun Solar Filed Solar + storage 7.4 mi 200

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution