Pacific Ethanol Stockton Cogen Plant — Power plant · Gas, combustion turbine · Pacific Ethanol Stockton LLCStockton 9 - slcva209 — Under construction · Solar · CA · 1 MW · 5.2 mi awayStockton 1 - slcva801 — Under construction · Solar · CA · 1 MW · 6.1 mi awayTracy Renewable Power Plant — Under construction · Biomass · CA · 5 MW · 12.7 mi away
  • Combustion
  • Wind & solar
  • Bioenergy
  • Under construction
  • Retired
  • 10 · 100 · 1,000 MW

Pacific Ethanol Stockton Cogen Plant

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbine Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2016
Net generation, 2020
0 MWh
Location
San Joaquin County, California
Operated by
Pacific Ethanol Stockton LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2016 to 2020
Fuel burned MMBtu by year, 2016 to 2020
  • Gas

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
Age
10 years since 2016
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeCISO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
July 2019
Capacity retired
4.8 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
PESCTNatural Gas Fired Combustion Turbine4.8 MWRetiredJuly 2019

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
CISO
Transmission lines within 15 mi (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit PESCT scheduled to retire, 4.8 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Stockton 9 - slcva209 Under construction Solar 5.2 mi 1
Stockton 1 - slcva801 Under construction Solar 6.1 mi 1
Tracy Renewable Power Plant Under construction Biomass 12.7 mi 5

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution