Parkers Lake 345 kV line
- Storage
- Loads
- Under construction
- Operating
- Size not stated
- Other infrastructure
- 10 · 100 · 1,000 MW
Map
- Storage
- Loads
- Under construction
- Operating
- Size not stated
- Other infrastructure
Parkers Lake 345 kV line: route and 11 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Parkers Lake 345 kV line
Transmission line
- Mapped route length
- Mapped route length: sourceLBNL · Open license, with creditmiles
- Voltage
- 345 kV
- States crossed
- US-MN
- Owner (as stated)
- Northern States Power Minnesota
Details
Who’s behind it
- Owner
- Northern States Power Minnesota
Interested in this project?
Set an alert
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
- Mapped route length (miles)
- 11
- Substations at the ends (as the source names them)
- Parkers Lake
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
| Attribute | Value |
|---|---|
| Owner, as the source states it | northern states power minnesota |
| HIFLD line ID | 150320 |
| Voltage class | 345 kV |
Sources
1 sourceSources LBNL
Sources
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
Around this line
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| DATA RECOGNITION CORP Built | Large load | 0.1 mi | |
| OPTUM TECHNOLOGY Built | Large load | 1.9 mi | |
| DATABANK MSP3 Built | Large load | 3.0 mi | |
| USS Zanzibar Solar LLC CSG Postponed | Solar | 4.6 mi | 1 |
| FIS GLOBAL Built | Large load | 6.0 mi | |
| SUPERCOMPUTER LLC Built | Large load | 8.6 mi | |
| TC Solar RCE Postponed | Solar | 10.3 mi | 1 |
| FAIRVIEW DATA CENTER Built | Large load | 11.3 mi | |
| UNITED HEALTH GROUP NEXT TECHNOLOGY CENTER Built | Large load | 13.8 mi | |
| Blue Lake BESS Under construction | Battery storage | 14.2 mi | 135.5 |
| HB FULLER CO - DATA CENTER - ARDEN HILLS Built | Large load | 14.4 mi |
Sources EPA ICIS-Air · EIA-860M