- Operating
- 10 · 100 · 1,000 MW
Map
- Clean firm
- Operating
Pelican: location. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Pelican
Power plant · Hydro
Key facts
Power plant · Hydroran 8% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1984
- Net generation, 2025
- 1,721 MWh
- Grid
- 2 kV to Pelican Utility
- Location
- Skagway Hoonah Angoon County, Alaska
- Operated by
- Pelican Utility
Output
- Oil
Details
Who’s behind it
- Owner
- City of Pelican
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Hydro source: “Conventional Hydroelectric”
- Age
- 42 years since 1984
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Eia status |
|
| Fuel burned (MMBtu), 2025 | 7,042 |
| Capacity factor, 2025 | 0.082 |
| Net generation (MWh), 2025 | 1,721 |
Data notes (1)
- Heat rate (Btu/kWh), 2025 not shown: computed 4091.8 outside 5000-30000 Btu/kWh
Retirement
EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.- Capacity retired
- 1.8 MW
- Generators retired
- 7
- Capacity still in service
- 2.4 MW
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| IC1 | Petroleum Liquids | 0.3 MW | Retired | December 2011 |
| IC2 | Petroleum Liquids | 0.1 MW | Retired | December 2011 |
| IC3 | Petroleum Liquids | 0.2 MW | Retired | December 2011 |
| IC4 | Petroleum Liquids | 0.2 MW | Retired | December 2011 |
| IC5 | Petroleum Liquids | 0.4 MW | Retired | December 2011 |
| IC8 | Petroleum Liquids | 0.2 MW | Retired | May 2024 |
| IC6 | Petroleum Liquids | 0.4 MW | Retired | November 2025 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 2 kV
- Transmission or distribution system owner
- Pelican Utility
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Pelican Utility | Operator | EIA-860M | ||
| City of Pelican | Owner | 100.0% | Dec 31, 2025 | EIA-860 |
Timeline
- Stated Unit IC6 scheduled to retire, 0.4 MW · EIA-860M
- Stated Unit IC8 scheduled to retire, 0.2 MW · EIA-860M
- Stated Units IC1, IC2, IC3, IC4, IC5 scheduled to retire, 1.2 MW · EIA-860M
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules