Pine — Power plant · Hydro · Wisconsin Electric Power Co
  • Clean firm
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Hydro

Key facts

Power plant · Hydroran 35% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1922
Net generation, 2025
11,108 MWh
Grid
69 kV to American Transmission Co (MISO)
Location
Florence County, Wisconsin
Operated by
Wisconsin Electric Power CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Hydro source: “Conventional Hydroelectric”
Age
104 years since 1922
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
RFC
Report year
2025
Grid voltage kv
69
Transmission owner
American Transmission Co
Balancing authority code
MISO
Balancing authority name
Midcontinent Independent Transmission System Operator, Inc..
Fuel burned (MMBtu), 202537,902
Capacity factor, 20250.352
Net generation (MWh), 202511,108
Balancing authority codeMISO

Timeline

  • In service · EIA-860M

Sources

3 sources

View at source