Show on map
Portola — Power plant · Oil · Sierra Pacific Power Co
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oil Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1965
Net generation, 2007
0 MWh
Grid
Sierra Pacific Power Co (NEVP)
Location
Plumas County, California
Operated by
Sierra Pacific Power CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2007
Fuel burned MMBtu by year, 2001 to 2007
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
61 years since 1965
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeNEVP

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
January 2007
Capacity retired
6 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Petroleum Liquids2 MWRetiredJanuary 2007
2Petroleum Liquids2 MWRetiredJanuary 2007
3Petroleum Liquids2 MWRetiredJanuary 2007

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Transmission or distribution system owner
Sierra Pacific Power Co
Balancing authority
Nevada Power Company
NERC region
WECC
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2, 3 scheduled to retire, 6 MW · EIA-860M
  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source