Show on map
Rawhide — Power plant · Gas, combustion turbine · Platte River Power Authority
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbineran 18% of 2024 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1984
Net generation, 2024
1,287,036 MWh
Grid
230 kV to Platte River Power Authority (PSCO)
Location
Larimer County, Colorado
Operated by
Platte River Power AuthoritySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Operations

Net generation, 2024
1,287,036MWh
Fuel burned, 2024
13,829,292MMBtu
Capacity factor, 2024
18.3%
Heat rate, 2024
10,745Btu/kWh
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
2026 (8 of 12 months)1,249,54914,040,265—11,236
2025 (11 of 12 months)1,333,88413,844,119—10,379
20241,287,03613,829,29218.3%10,745
20231,501,54616,115,30421.4%10,732
20222,141,72421,883,99630.6%10,218
20211,864,21019,432,68526.6%10,424
20202,032,32020,956,76428.9%10,312
20192,037,51920,821,17729.1%10,219
20181,870,84919,026,67126.7%10,170
20172,234,07122,518,26731.9%10,080
20162,258,59822,905,21032.1%10,141
20151,990,33420,196,12828.4%10,147
20142,189,61422,153,73231.2%10,118
20132,406,77824,124,19734.3%10,023
20122,148,27121,336,63730.6%9,932
20112,306,80822,985,70232.9%9,964
20102,270,39222,959,36332.4%10,112
20092,382,19124,045,64734.0%10,094
20082,161,89522,211,63030.8%10,274
20072,344,88424,158,89133.4%10,303
20062,210,39322,671,76931.5%10,257
20051,942,10920,062,37427.7%10,330
20042,289,74423,751,56732.6%10,373
20032,289,36524,014,41732.6%10,490
20022,078,17521,738,89829.6%10,461
20012,193,00423,163,88931.3%10,563
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

3 sources

Sources EIA-860M · GEM · EIA

Sources

Every source and license · Attribution

View at source