Show on map
RE Tranquillity — Power plant · Solar · Southern Power Co
  • Wind & solar
  • Operating
  • 10 · 100 · 1,000 MW

RE Tranquillity

Power plant · Solar

Key facts

Power plant · Solarran 20% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2016
Net generation, 2025
484,790 MWh
Grid
230 kV to Pacific Gas & Electric Co (CISO)
Location
Fresno County, California

Operations

Net generation, 2025
484,790MWh
Fuel burned, 2025
1,689,189MMBtu
Capacity factor, 2025
20.0%
Heat rate, 2025
Not stated
Capacity factor % of full output, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
2025484,7901,689,18920.0%—
2024491,4351,712,74420.2%—
2023450,4481,566,97218.5%—
2022424,9171,484,53417.5%—
2021486,5924,308,18620.0%—
2020428,1083,753,22417.6%—
2019493,3654,393,41520.3%—
2018501,8194,568,55920.7%—
2017455,4314,195,88818.8%—
2016 (6 of 12 months)207,8291,918,676——
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

3 sources

Sources EIA-860M · GEM · EIA

Sources

Every source and license · Attribution

View at source