Rhinelander Mill — Power plant · Gas, steam turbine · Ahlstrom-Munksjo
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Rhinelander Mill

Power plant · Gas, steam turbine

Key facts

Power plant · Gas, steam turbineran 3% of 2025 Out of service
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1917
Net generation, 2025
5,817 MWh
Grid
115 kV to Wisconsin Public Service Corp (MISO)
Location
Oneida County, Wisconsin
Operated by
Ahlstrom-Munksjo

Output

Net generation MWh by year, 2001 to 2026
Fuel burned MMBtu by year, 2001 to 2026
  • Gas
  • Coal
  • Oil
  • Unspecified fuel

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, steam turbine source: “Natural Gas Steam Turbine”
Age
109 years since 1917
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110070736574
Subparts reported
C
NAICS code
322120
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1005991
Eia status
By code
OP
Mw
1
Units
2
OS
Mw
20.30
Units
3
Standby mw
0
Status rule
majority_mw_out_of_service
In service mw
21.30
Out of service mw
20.30
Fuel burned (MMBtu), 20252,128,711
Capacity factor, 20250.031
Net generation (MWh), 20255,817
Balancing authority codeMISO
Data notes (1)
  • Heat rate (Btu/kWh), 2025 not shown: computed 365946.5 outside 5000-30000 Btu/kWh

Retirement

Capacity retired
4 MW
Generators retired
1
Capacity still in service
21.3 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN3Natural Gas Steam Turbine4 MWRetiredDecember 2012

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
115 kV
Transmission or distribution system owner
Wisconsin Public Service Corp
Balancing authority
Midcontinent Independent Transmission System Operator, Inc..
NERC region
MRO
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Ahlstrom-Munksjo Operator EIA-860M
AHLSTROM-MUNKSJO NORTH AMERICA SPECIALTY SOLUTIONS LLC Owner 100.0% Dec 31, 2023 EPA GHGRP

Timeline

  • Stated Unit GEN3 scheduled to retire, 4 MW · EIA-860M
  • In service · EIA-860M