Show on map
Rockport (MO) — Power plant · Gas, reciprocating engine · City of Rockport - (MO)
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Rockport (MO)

Power plant · Gas, reciprocating engine

Key facts

Power plant · Gas, reciprocating engine Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1940
Net generation, 2012
0 MWh
Location
Atchison County, Missouri
Operated by
City of Rockport - (MO)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2012
Fuel burned MMBtu by year, 2001 to 2012
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, reciprocating engine source: “Natural Gas Internal Combustion Engine”
Age
86 years since 1940
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeAECI

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
November 2011
Capacity retired
5.7 MW
Generators retired
6
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Natural Gas Internal Combustion Engine1.1 MWRetiredNovember 2011
2Natural Gas Internal Combustion Engine1.1 MWRetiredNovember 2011
3Petroleum Liquids0.5 MWRetiredNovember 2011
4Petroleum Liquids0.4 MWRetiredNovember 2011
5Natural Gas Internal Combustion Engine1.3 MWRetiredNovember 2011
6Natural Gas Internal Combustion Engine1.3 MWRetiredNovember 2011
By technology
Nameplate capacity retired or scheduled to retire, by technology
TechnologyRetiredScheduled to retire
Natural Gas Internal Combustion Engine4.8 MW
Petroleum Liquids0.9 MW

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
AECI
Transmission lines within 15 mi (4)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2, 3, 4, 5, 6 scheduled to retire, 5.7 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source