Show on map
Sequoyah — Power plant · Nuclear · Tennessee Valley Authority
  • Clean firm
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Nuclear

Key facts

Power plant · Nuclearran 61% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1981
Net generation, 2025
13,059,930 MWh
Grid
500 kV to Tennessee Valley Authority (TVA)
Location
Hamilton County, Tennessee
Operated by
Tennessee Valley AuthoritySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Operations

Net generation, 2025
13,059,930MWh
Fuel burned, 2025
136,644,496MMBtu
Capacity factor, 2025
61.1%
Heat rate, 2025
10,463Btu/kWh
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
2026 (8 of 12 months)13,221,780138,075,047—10,443
202513,059,930136,644,49661.1%10,463
202413,427,277140,579,44562.6%10,470
202319,227,596200,967,96489.9%10,452
202218,827,299196,700,44888.0%10,448
202117,654,812184,124,02882.6%10,429
202019,099,189199,509,71389.1%10,446
201918,064,619188,624,28984.5%10,442
201817,703,749185,086,47582.8%10,455
201718,241,299190,883,96285.3%10,464
201617,242,608180,610,23880.4%10,475
201516,511,322172,683,62377.2%10,458
201418,892,391197,597,61688.3%10,459
201318,526,011193,573,45186.6%10,449
201216,585,630173,794,06677.3%10,479
201118,688,193195,553,25487.4%10,464
201018,000,764188,143,98684.2%10,452
200917,754,536186,209,57283.0%10,488
200818,917,308198,404,72888.2%10,488
200718,650,685195,552,43387.2%10,485
200618,000,679187,819,08484.2%10,434
200518,999,153198,256,16288.8%10,435
200418,755,368195,562,22287.5%10,427
200315,603,769162,606,87773.0%10,421
200218,495,572193,130,76486.5%10,442
200118,949,856197,874,39588.6%10,442
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

3 sources

Sources EIA-860M · GEM · EIA

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • GEMOpen license, with credit · retrieved Oct 26, 2026Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)

Every source and license · Attribution