Sierra Nevada Brewing Co Hybrid
Power plant · Gas, combustion turbine
Key facts
Power plant · Gas, combustion turbineran 29% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2007
- Net generation, 2025
- 10,690 MWh
- Grid
- 12 kV to Pacific Gas & Electric Co (CISO)
- Location
- Butte County, California
- Operated by
- Sierra Nevada Brewing CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
- Biomass and waste
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
- Age
- 19 years since 2007
- Unused energy
- 26 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 13,129 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| Fuel burned (MMBtu), 2025 | 140,346 |
| Capacity factor, 2025 | 0.291 |
| Heat rate (Btu/kWh), 2025 | 13,128.7 |
| Net generation (MWh), 2025 | 10,690 |
| Balancing authority code | CISO |
Solar arrays
Solar arrays
The array area counts panels and inverters only, not buildings, fences or the whole site.
- Array area (acres)
- 6.7
- AC capacity (MW)
- 1.7
- DC capacity (MW)
- 2
- Mounting
- Single-axis tracking
- Site type
- Greenfield
- Began operating
- 2007
Retirement
EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.- Capacity retired
- 1 MW
- Generators retired
- 1
- Capacity still in service
- 4.2 MW
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| FCE | Other Natural Gas | 1 MW | Retired | May 2015 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 12 kV
- Transmission or distribution system owner
- Pacific Gas & Electric Co
- Balancing authority
- California Independent System Operator
- NERC region
- WECC
Transmission lines within 15 mi (10)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Unit FCE scheduled to retire, 1 MW · EIA-860M
- In service · EIA-860M
Sources
6 sourcesSources EIA-860M · GEM · LBNL · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- USPVDBMap services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant