Solar Photovoltaic Project #22
Power plant · Solar
Key facts
Power plant · Solarran 0% of 2023 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2011
- Net generation, 2023
- 8 MWh
- Grid
- 12 kV to Southern California Edison Co (CISO)
- Location
- San Bernardino County, California
- Operated by
- Southern California Edison CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Operations
- Net generation, 2023
- 8
MWh - Fuel burned, 2023
- 28
MMBtu - Capacity factor, 2023
- 0.1
% - Heat rate, 2023
- Not stated
| Year | Net generation (MWh) | Fuel burned (MMBtu) | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|---|
| 2023 | 8 | 28 | 0.1% | — |
| 2022 | 402 | 1,370 | 2.3% | — |
| 2021 | 679 | 6,005 | 3.9% | — |
| 2020 | 1,726 | 15,134 | 9.8% | — |
| 2019 | 1,719 | 15,308 | 9.8% | — |
| 2018 | 2,547 | 23,187 | 14.5% | — |
| 2017 | 2,754 | 25,372 | 15.7% | — |
| 2016 | 2,800 | 25,850 | 15.9% | — |
| 2015 | 3,409 | 31,770 | 19.5% | — |
| 2014 | 3,059 | 29,092 | 17.5% | — |
| 2013 | 3,620 | 34,537 | 20.7% | — |
| 2012 | 2,160 | 20,555 | 12.3% | — |
| 2011 | 3,095 | 30,071 | 17.7% | — |
How these are worked out
Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.