Show on map
Superior Falls — Power plant · Hydro · Northern States Power Co - Minnesota
  • Clean firm
  • Operating
  • 10 · 100 · 1,000 MW

Superior Falls

Power plant · Hydro

Key facts

Power plant · Hydroran 67% of 2025 Retiring
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1917
Net generation, 2025
8,176 MWh
Grid
34 kV to Northern States Power Co (MISO)
Location
Gogebic County, Michigan
Operated by
Northern States Power Co - MinnesotaSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Hydro source: “Conventional Hydroelectric”
Age
109 years since 1917
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Fuel burned (MMBtu), 202527,896
Capacity factor, 20250.667
Net generation (MWh), 20258,176
Balancing authority codeMISO

Retirement

EIA-860M September 2026StatusAt least half of the plant's in-service nameplate capacity is scheduled to retire, on dates its owner has reported to EIA. As of EIA-860M for September 2026.
Next scheduled retirement
December 2064
Capacity scheduled to retire
1.4 MW
Generators scheduled to retire
2
Share of in-service capacity scheduled
100%
Capacity still in service
1.4 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Conventional Hydroelectric0.7 MWScheduled to retireDecember 2064
2Conventional Hydroelectric0.7 MWScheduled to retireDecember 2064

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
34 kV
Transmission or distribution system owner
Northern States Power Co
Balancing authority
Midcontinent Independent Transmission System Operator, Inc..
NERC region
RFC
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2 scheduled to retire, 1.4 MW · EIA-860M
  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution