Tesla
Power plant · Hydro
Key facts
Power plant · Hydroran 21% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1997
- Net generation, 2025
- 48,399 MWh
- Grid
- 34 kV to City of Colorado Springs - (CO) (WACM)
- Location
- El Paso County, Colorado
- Operated by
- City of Colorado Springs - (CO)SourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Hydro source: “Conventional Hydroelectric”
- Age
- 29 years since 1997
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 165,139 |
| Capacity factor, 2025 | 0.208 |
| Net generation (MWh), 2025 | 48,399 |
| Balancing authority code | WACM |
Timeline
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| NOVVA COLORADO - DATA CENTER CO SPRINGS Built | Large load | 8.7 km | |
| QTS COLORADO SPRINGS I - DATA CENTER Built | Large load | 8.9 km | |
| VERIZON WIRELESS - DATA CENTER Built | Large load | 9.2 km | |
| COS02 DATA CENTER Built | Large load | 10.0 km | |
| COS01 DATA CENTER Built | Large load | 21.7 km | |
| VINEYARD DATA CENTER Built | Large load | 23.1 km |