Show on map
TMC LLC — Power plant · Biomass · TMC LLCBailey Mill Solar — Solar · FL · 74.9 MW · 11.7 km away
  • Wind & solar
  • Bioenergy
  • Under construction
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Biomass

Key facts

Power plant · Biomass Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1990
Net generation, 2011
0 MWh
Location
Jefferson County, Florida
Operated by
TMC LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2012
Fuel burned MMBtu by year, 2001 to 2012
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Wood/Wood Waste Biomass”
Age
36 years since 1990

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
March 2012
Capacity retired
7.5 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN1Wood/Wood Waste Biomass7.5 MWRetiredMarch 2012

Grid

Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit GEN1 scheduled to retire, 7.5 MW · EIA-860M
  • In service · EIA-860M

Sources

3 sources

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Bailey Mill Solar Under construction Solar 11.7 km 74.9

Sources EIA-860M

Sources

Attribution