Tracy 210: location and 13 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Tracy 210
Power plant · Gas, other
Key facts
Power plant · Gas, otherran 91% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2019
- Net generation, 2025
- 20,617 MWh
- Grid
- 12 kV to Pacific Gas & Electric Co. (CISO)
- Location
- San Joaquin County, California
- Operated by
- Costco WholesaleSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, other source: “Other Natural Gas”
- Age
- 7 years since 2019
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 1,501,457 |
| Capacity factor, 2025 | 0.905 |
| Net generation (MWh), 2025 | 20,617 |
| Balancing authority code | CISO |
Data notes (1)
- Heat rate (Btu/kWh), 2025 not shown: computed 72826.2 outside 5000-30000 Btu/kWh
Timeline
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| TESLA Power Project Postponed | Gas, combined cycle | 3.2 km | 1,322 |
| Tracy BESS Under construction | Storage | 3.8 km | 40 |
| Zeus BESS Contracted | Storage | 3.9 km | 200 |
| Mulqueeney Wind Energy Under construction | Wind | 5.8 km | 80 |
| Sand Hill B Filed | Wind | 6.9 km | 17 |
| Sand Hill A Filed | Wind | 7.2 km | 13.5 |
| Sand Hill C Contracted | Wind | 7.8 km | 80.8 |
| Rooney Ranch Filed | Wind | 10.8 km | 21 |
| Tracy Renewable Power Plant Under construction | Biomass | 10.8 km | 5 |
| Buena Vista Energy LLC Postponed | Storage | 15.1 km | 100 |
| Tres Vaqueros Wind Farms LLC Withdrawn | Wind | 19.2 km | 28.3 |
| Aramis I Solar Project × 2 units Under construction | Storage | 20.9 km | 200 |
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- CAISO Public Queue ReportSource: California ISO