- Combustion
- Retired
- 10 · 100 · 1,000 MW
Map
- Combustion
- Retired
US DOE Savannah River Site (D Area): location and 2 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
US DOE Savannah River Site (D Area)
Power plant · Coal
Key facts
Power plant · Coalran 4% of 2012 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1952
- Net generation, 2012
- 26,198 MWh
- Location
- Aiken County, South Carolina
- Operated by
- Savannah River Nuclear Solutions LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Coal
- Oil
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Coal source: “Conventional Steam Coal”
- Age
- 74 years since 1952
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- April 2012
- Capacity retired
- 78.2 MW
- Generators retired
- 7
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| HP-1 | Conventional Steam Coal | 9.4 MW | Retired | April 2012 |
| HP-2 | Conventional Steam Coal | 9.4 MW | Retired | April 2012 |
| HP-3 | Conventional Steam Coal | 9.4 MW | Retired | April 2012 |
| LP-1 | Conventional Steam Coal | 12.5 MW | Retired | April 2012 |
| LP-2 | Conventional Steam Coal | 12.5 MW | Retired | April 2012 |
| LP-3 | Conventional Steam Coal | 12.5 MW | Retired | April 2012 |
| LP-4 | Conventional Steam Coal | 12.5 MW | Retired | April 2012 |
Grid
Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.Transmission lines within 15 mi (10)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Units HP-1, HP-2, HP-3, LP-1, LP-2, LP-3, LP-4 scheduled to retire, 78.2 MW · EIA-860M
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Jackson Solar Postponed | Solar | 7.8 mi | 14 |
| Foreman Solar Postponed | Solar | 12.8 mi | 6.4 |
Sources EIA-860M