Verdi
Power plant · Hydro
Key facts
Power plant · Hydroran 90% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1911
- Net generation, 2025
- 18,977 MWh
- Grid
- 25 kV to Sierra Pacific Power Co (NEVP)
- Location
- Washoe County, Nevada
- Operated by
- Truckee Meadows Water AuthoritySourceEIA-860M Preliminary Monthly Electric Generator Inventory
Operations
- Net generation, 2025
- 18,977
MWh - Fuel burned, 2025
- 64,749
MMBtu - Capacity factor, 2025
- 90.3
% - Heat rate, 2025
- Not stated
| Year | Net generation (MWh) | Fuel burned (MMBtu) | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|---|
| 2026 (8 of 12 months) | 10,090 | 34,427 | — | — |
| 2025 | 18,977 | 64,749 | 90.3% | — |
| 2024 | 19,083 | 65,110 | 90.5% | — |
| 2023 | 17,843 | 60,880 | 84.9% | — |
| 2022 | 15,105 | 51,538 | 71.9% | — |
| 2021 | 12,129 | 107,268 | 57.7% | — |
| 2020 | 15,768 | 138,239 | 74.8% | — |
| 2019 | 17,364 | 154,626 | 82.6% | — |
| 2018 | 17,043 | 155,156 | 81.1% | — |
| 2017 | 17,742 | 163,458 | 84.4% | — |
| 2016 | 13,993 | 129,184 | 66.4% | — |
| 2015 | 4,013 | 37,398 | 19.1% | — |
| 2014 | 10,700 | 101,756 | 50.9% | — |
| 2013 | 17,756 | 169,410 | 84.5% | — |
| 2012 | 18,962 | 180,443 | 90.0% | — |
| 2011 | 17,935 | 174,258 | 85.3% | — |
| 2010 | 16,136 | 157,422 | 76.8% | — |
| 2009 | 13,591 | 132,645 | 64.6% | — |
| 2008 | 17,275 | 170,228 | 81.9% | — |
| 2007 | 17,531 | 173,277 | 83.4% | — |
| 2006 | 14,574 | 144,558 | 69.3% | — |
| 2005 | 7,635 | 76,342 | 36.3% | — |
| 2004 | -19 | -190 | — | — |
| 2003 | 15,292 | 156,605 | 72.7% | — |
| 2002 | 14,931 | 151,893 | 71.0% | — |
| 2001 | 15,006 | 155,057 | 71.4% | — |
How these are worked out
Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.