WAL752 — Power plant · Gas, reciprocating engine · Walmart Stores Texas, LLCTX LaPort 10060 Porter Road Solar — Solar · TX · 1.6 MW · 10.0 km awayNET Power La Porte Station — Gas, combustion turbine · TX · 25.5 MW · 10.4 km awayTexas Petrochemicals — Gas, combined cycle · TX · 560 MW · 10.7 km awayBerkman Storage — Storage · TX · 100 MW · 18.0 km awayGreens Bayou 6 — Gas, combustion turbine · TX · 445 MW · 20.2 km awayHidden Lakes — Storage · TX · 9.9 MW · 21.2 km awayTX Houston 7080 Express Lane — Storage · TX · 1.5 MW · 21.5 km awayBaytown — Biomass · TX · 1.3 MW · 24.1 km awayGCCISD NEW TECHNOLOGY DATA CENTER — Large load · TX · 24.9 km away
  • Combustion
  • Loads
  • In development
  • Under construction
  • Operating
  • Stage not stated
  • Size not stated
  • 10 · 100 · 1,000 MW

Power plant · Gas, reciprocating engine

Key facts

Power plant · Gas, reciprocating engineran 1% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2020
Net generation, 2025
75 MWh
Grid
0.5 kV to CenterPoint Energy (ERCO)
Location
Harris County, Texas
Operated by
Walmart Stores Texas, LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2021 to 2025
Fuel burned MMBtu by year, 2021 to 2025
  • Gas

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, reciprocating engine source: “Natural Gas Internal Combustion Engine”
Age
6 years since 2020
Unused energy
10 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
10,053 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
TRE
Report year
2025
Grid voltage kv
0.500
Transmission owner
CenterPoint Energy
Balancing authority code
ERCO
Balancing authority name
Electric Reliability Council of Texas, Inc.
Fuel burned (MMBtu), 2025754
Capacity factor, 20250.007
Heat rate (Btu/kWh), 202510,053.3
Net generation (MWh), 202575
Balancing authority codeERCO

Timeline

  • In service · EIA-860M

Sources

3 sources

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
TX LaPort 10060 Porter Road Solar Postponed Solar 10.0 km 1.6
NET Power La Porte Station Studied Gas, combustion turbine 10.4 km 25.5
Texas Petrochemicals Postponed Gas, combined cycle 10.7 km 560
Berkman Storage Postponed Storage 18.0 km 100
Greens Bayou 6 Under construction Gas, combustion turbine 20.2 km 445
Hidden Lakes Postponed Storage 21.2 km 9.9
TX Houston 7080 Express Lane Postponed Storage 21.5 km 1.5
Baytown Postponed Biomass 24.1 km 1.3
GCCISD NEW TECHNOLOGY DATA CENTER Unknown Large load 24.9 km