Show on map
Warm Springs Forest Products — Power plant · Biomass · Warm Springs Forest Prod IndstSalmonfly Solar and Storage — Filed · Solar + storage · OR · 494 MW · 11.6 mi away
  • Wind & solar
  • Bioenergy
  • In development
  • Retired
  • 10 · 100 · 1,000 MW

Warm Springs Forest Products

Power plant · Biomass

Key facts

Power plant · Biomassran 1% of 2015 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1977
Net generation, 2015
1,024 MWh
Location
Jefferson County, Oregon
Operated by
Warm Springs Forest Prod IndstSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2015
Fuel burned MMBtu by year, 2001 to 2015
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Wood/Wood Waste Biomass”
Age
49 years since 1977
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codePACW

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
March 2016
Capacity retired
9 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN1Wood/Wood Waste Biomass3 MWRetiredMarch 2016
GEN2Wood/Wood Waste Biomass3 MWRetiredMarch 2016
GEN3Wood/Wood Waste Biomass3 MWRetiredMarch 2016

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
PACW
Transmission lines within 15 mi (2)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units GEN1, GEN2, GEN3 scheduled to retire, 9 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Salmonfly Solar and Storage Filed Solar + storage 11.6 mi 494

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution