Westwind Trust
Power plant · Wind
Key facts
Power plant · Windran 7% of 2015 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1986
- Net generation, 2015
- 9,657 MWh
- Location
- Riverside County, California
- Operated by
- New Dimension Energy Company, LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Wind source: “Onshore Wind Turbine”
- Age
- 40 years since 1986
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Balancing authority code | CISO |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- December 2017
- Capacity retired
- 16 MW
- Generators retired
- 1
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| WIN1 | Onshore Wind Turbine | 16 MW | Retired | December 2017 |
Grid
EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).- Balancing authority
- CISO
Transmission lines within 25 km (10)
Connection points within 25 km (1)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Unit WIN1 scheduled to retire, 16 MW · EIA-860M
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · LBNL · CAISO · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- CAISOSource: California ISO
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Westwind Trust unit WTGS Postponed | Wind | 0.0 km | 15.6 |
| Painted Hills Postponed | Wind | 8.4 km | 17.5 |
| Painted Hills IV Wind Withdrawn | Wind | 8.9 km | 19.5 |
| Solar Photovoltaic Project #45 Postponed | Solar | 11.3 km | 6 |
| Alta Mesa Project Phase IV Postponed | Wind | 12.1 km | 40 |