Wheelabrator Frackville Energy
Power plant · Coal
Key facts
Power plant · Coalran 12% of 2020 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1988
- Net generation, 2020
- 50,671 MWh
- Grid
- 69 kV to PPL Electric Utilities Corp (PJM)
- Location
- Schuylkill County, Pennsylvania
- Operated by
- Wheelabrator Environmental Systems
Output
- Coal
- Oil
Details
Who’s behind it
Interested in this project?
- Technology
- Coal source: “Conventional Steam Coal”
- Age
- 38 years since 1988
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| EPA greenhouse gas reporting (GHGRP) |
|
| Balancing authority code | PJM |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- February 2020
- Capacity retired
- 48 MW
- Generators retired
- 1
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| GEN1 | Conventional Steam Coal | 48 MW | Retired | February 2020 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 69 kV
- Transmission or distribution system owner
- PPL Electric Utilities Corp
- Balancing authority
- PJM Interconnection, LLC
- NERC region
- RFC
Transmission lines within 15 mi (5)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| WHEELABRATOR TECHNOLOGIES HOLDINGS INC | Owner | 100.0% | Dec 31, 2023 | EPA GHGRP |
| Wheelabrator Environmental Systems | Operator | EIA-860M |
Timeline
- Stated Unit GEN1 scheduled to retire, 48 MW · EIA-860M
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · LBNL · EIA · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT) · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| WMPI Pty LLC Postponed | Coal | 10.3 mi | 41 |
| PF Onsite BESS Filed | Battery storage | 10.7 mi | 21 |
| Data Center Filed | Large load | 14.7 mi |
Sources EIA-860M · FAA OE/AAA