Show on map
Youngs Creek Hydroelectric Project — Power plant · Hydro · PUD No 1 of Snohomish County - (WA)
  • Clean firm
  • Operating
  • 10 · 100 · 1,000 MW

Youngs Creek Hydroelectric Project

Power plant · Hydro

Key facts

Power plant · Hydroran 20% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2011
Net generation, 2025
12,850 MWh
Grid
12 kV to PUD 1 of Snohomish County (BPAT)
Location
Snohomish County, Washington
Operated by
PUD No 1 of Snohomish County - (WA)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2011 to 2025

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Hydro source: “Conventional Hydroelectric”
Age
15 years since 2011
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
WECC
Report year
2025
Grid voltage kv
12.50
Transmission owner
PUD 1 of Snohomish County
Balancing authority code
BPAT
Balancing authority name
Bonneville Power Administration
Fuel burned (MMBtu), 202543,842
Capacity factor, 20250.196
Net generation (MWh), 202512,850
Balancing authority codeBPAT

Timeline

  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source