Jindal Power Ltd
Power plant owner
Key facts
Power plant owner · 300 MW- Capacity held
- 300MW
- Assets
- 1
- Projects
- 3
- Companies below
- 2
- Registered in
- United States
- Parent
- No parent recordedNo parent recordedLike 48,145 of 50,298 companies here. Why
Projects 3
Capacity
1.67 GW
none active
| Status | Name. Sort by name, A to Z | Type | MW, sorted descending. Sort by capacity, smallest first | State | Online. Sort by proposed online date, latest first | Source |
|---|---|---|---|---|---|---|
| Canceled | Jamunda power station Unit 2 | Coal | 660 MW | India | — | Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses) |
| Canceled | Jamunda power station Unit 1 | Coal | 660 MW | India | — | Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses) |
| Unknown | Liwonde power station Unit 1 | Coal | 350 MW | Malawi | — | Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses) |
Sources GEM
Assets 1
Assets
1
Capacity
300 MW
- Coal: 300 MW, 1 asset
Owns 1 power plant
| Name. Sort by name, A to Z | Type. Sort by type, A to Z | Role. Sort by role, A to Z | MW, sorted descending. Sort by capacity, smallest first | State. Sort by state, A to Z | Share | Held by |
|---|---|---|---|---|---|---|
| Nardana Vaghode power station | Coal | Owns | 300 MW | — | 100.0% | Jindal Power Ltd |
Sources GEM
Sources
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
Ownership 3
Companies
3
this one included
Parents
0
Subsidiaries
2
direct
Assets are what each company holds itself. A dash: this view does not show it; the company’s own page does.
-
Jindal Power Ltd This company 3 assets2,220 MWwith the companies below
-
Jindal Jhajjar Power Ltd Subsidiary · share not stated 1 asset1,320 MW
-
Simhapuri Energy Ltd Subsidiary · share not stated 1 asset600 MW
-
The same companies as a table, with each ownership claim
| Company. Sort by company, A to Z | Relationship, sorted ascending. Sort by relationship, subsidiaries first | Assets. Sort by assets held, largest first | Asset types |
|---|---|---|---|
| Jindal Power Ltd | This company | 1 | power plant |
| Jindal Jhajjar Power Ltd | Subsidiary | — | — |
| Simhapuri Energy Ltd | Subsidiary | — | — |
Sources 1
Registers
1
Reuse terms
- 1 Open license, with credit
Latest read
2026-10-26
From its recordsSourcesThe registers behind this company's assets, projects and RFPs; the company record itself is derived from them.
Sources
-
View at source →
GEM ·
Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses)
Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License. · license
In-file notice, About sheet of Global_Integrated_Power_September_2026_V2.xlsb (the owner's download, read 2026-10-26 with pyxlsb 1.0.10; decisions log 2026-10-26): "Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License. (See the CC license for attribution requirements if sharing or adapting the data set.)" and "Please note records with a “TZ ID” in the Other IDs (unit/phase) column were partially or fully sourced from the TransitionZero, Solar Asset Mapper, August 2025. Copyright © TransitionZero, Solar Asset Mapper, August 2025. Distributed under a Creative Commons Attribution-Non-Commercial 4.0 International License (CC BY-NC 4.0)." Before it was read: no licence prose on the dataset page (retrieved 2026-10-23), which gives only "The recommended citation is "Global Integrated Power Tracker, Global Energy Monitor, September 2026 release.""; GEM's download form records "Creative Commons Attribution 4.0 International (CC BY 4.0) — /creative-commons-license" (https://api.globalenergymonitor.org/static/gem-download-form.bundle.js, sha256 e5ecbeab…905e5b, retrieved 2026-10-23).
Summary only: the source’s license keeps the full record at the source.