NextEra Energy Resources Interconnection Holdings, LLC

Follow this company

Key facts

5 projects
Projects
5projects
Registered in
United States
Parent
NextEra EnergyOwnership claimOwnership link recorded from the companies' own published statements; no date stated by the source.

Projects 5

9 possible duplicatesPossible duplicatesThese queue requests name no project and may be a plant already listed, so they are not counted.

Projects sponsored by this company, sorted by capacity, largest first.
Status Name. Sort by name, A to Z Type MW, sorted descending. Sort by capacity, smallest first State Online. Sort by proposed online date, latest first Source
Contracted NextEra Energy Resources Interconnection Holdings, LLC Solar + storage 600 MW ID Online Oct 1, 2030 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Studied Trumpet Solar Solar 533 MW TX Online Jul 1, 2030 ERCOT
Studied Capshaw Solar Solar 450 MW TX Online Jul 1, 2030 ERCOT
Contracted Slager Lake Wind Wind 310.2 MW TX Online Jul 1, 2029 ERCOT
Withdrawn NextEra Energy Resources Interconnection Holdings, LLC Solar + storage 300 MW ID — LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Contracted NextEra Energy Resources Interconnection Holdings, LLC Storage 300 MW ID Online Dec 31, 2025 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Contracted NextEra Energy Resources Interconnection Holdings, LLC Solar + storage 300 MW WY Online Jun 1, 2025 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Contracted NextEra Energy Resources Interconnection Holdings, LLC Solar + storage 300 MW WY Online Jun 1, 2025 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Contracted NextEra Energy Resources Interconnection Holdings, LLC Solar + storage 300 MW ID Online Oct 1, 2027 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Contracted NextEra Energy Resources Interconnection Holdings, LLC Solar + storage 300 MW WY Online Dec 31, 2025 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Contracted NextEra Energy Resources Interconnection Holdings, LLC Solar + storage 300 MW WY Online Dec 31, 2025 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Contracted NextEra Energy Resources Interconnection Holdings, LLC Storage 200 MW ID Online Jun 1, 2027 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Contracted NextEra Energy Resources Interconnection Holdings, LLC Solar + storage 200 MW WY Online Jun 1, 2025 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built NextEra Energy Resources Interconnection Holdings, LLC Wind 150 MW WY Online Dec 31, 2023 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)

Sources Berkeley Lab · ERCOT

Sources

Every source and license · Attribution