As filed: SCPSA

Key facts

22 projects
Projects
22projects
Registered in
United States
Parent
No parent recordedNo parent recordedLike 48,118 of 50,271 companies here. Why

Projects 22

Projects sponsored by this company, sorted by capacity, largest first.
Status Name. Sort by name, A to Z Type MW, sorted descending. Sort by capacity, smallest first State Online. Sort by proposed online date, latest first Source
Built SCPSA Gas, other 882 MW SC Online 1 Mar 2002 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 620 MW SC Online 17 Jun 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Withdrawn SCPSA Coal 609 MW SC Online 1 Jan 2013 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Withdrawn SCPSA Coal 609 MW SC Online 1 Jan 2012 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 600 MW SC Online 1 Jun 2009 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 600 MW SC Online 1 Jun 2006 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 540 MW SC Online 5 Jun 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 306 MW SC Online 23 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 295 MW SC Online 28 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 295 MW SC Online 2 Jun 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 295 MW SC Online 30 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Gas, other 273 MW SC Online 1 Jan 2004 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 270 MW SC Online 3 Jun 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Coal 170 MW SC Online 19 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Hydro 128 MW SC Online 25 Apr 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Oil 92 MW SC Online 7 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Oil 70 MW SC Online 1 Jun 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Oil 50 MW SC Online 25 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Oil 35 MW SC Online 29 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Oil 25 MW SC Online 27 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Oil 25 MW SC Online 26 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Built SCPSA Oil 22 MW SC Online 15 May 2005 LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)